Judgment / Reference Class Forecasting
Reference Class Forecasting
Choose comparable projects, collect actual outcomes, build a distribution, then estimate at a level of risk you can afford.
All values below are constructed teaching data, not industry statistics or a basis for real commitments.
Risks to examine: Scope changes, data quality, integration complexity and lack of adoption
2
3
3
4
4
5
5
6
7
9
11
15
Each bar is one project · Unit: months12 samples
EXPERIMENT RESULT
P80 · 8.6 months
Approximately 80% of sample durations lie at or below this percentile position (linear interpolation). This is not your project's probability of success.
Small samples, selection bias and changing conditions weaken predictive value. If projects are not comparable, collect better data first.
MAKE IT CONCRETE
What would this look like in everyday life?
For a small booking system, compare similarly sized systems delivered by similar teams before looking at all software projects.