Judgment / Outside View
Zoom Out
Set your project's story aside and examine the distribution of outcomes in comparable projects. Uniqueness does not erase shared risks.
All values below are constructed teaching data, not industry statistics or a basis for real commitments.
Risks to examine: Scope changes, data quality, integration complexity and lack of adoption
2
3
3
4
4
5
5
6
7
9
11
15
Each bar is one project · Unit: months12 samples
EXPERIMENT RESULT
P80 · 8.6 months
Approximately 80% of sample durations lie at or below this percentile position (linear interpolation). This is not your project's probability of success.
Small samples, selection bias and changing conditions weaken predictive value. If projects are not comparable, collect better data first.
MAKE IT CONCRETE
What would this look like in everyday life?
Before estimating a renovation, ask owners of both completed and delayed projects, not just the contractor's smoothest examples.